Engagement model

FAT and expediting campaign

For the last three months of a machinery or equipment order, when most delays and functional problems surface.

Typical engagement modelThis page describes how such a programme is usually structured. It is not a client case study and contains no client data.

01Situation

A special machine is in assembly with bought-out items still arriving, the FAT date is approaching and the buyer's engineers need to plan their trip.

02Scope of the programme

  1. Assembly expediting

    Bought-out items and assembly progress verified weekly.

  2. Readiness check

    Pre-FAT visit confirms the machine is complete and internally tested.

  3. FAT

    Test procedure reviewed; FAT witnessed with or without buyer engineers.

  4. Punch list

    Open items tracked and verified.

  5. Shipment

    Preservation, crating and loading supervised.

03Reporting and deliverables

  • Weekly expediting reports
  • Readiness confirmation
  • FAT report
  • Punch list closure report
  • Loading report

04What the buyer gains

  • No wasted FAT trips
  • Functional problems fixed at the factory
  • Shipment on the planned date
  • Clear acceptance record

Direct contact. No forms.

Discuss your inspection, audit or project requirements

Send us the purchase order scope, drawings, specifications or ITP and the supplier location. You will receive a written proposal with scope, inspector profile, schedule and reporting format.

Emailinfo@qualitas.tr Telephone+90 533 197 19 81
OfficeBeştepe Mah. Nergiz Sok. 7/2 Kat:3 No: 87, Yenimahalle, Ankara, Turkey