01Fabrication is welding plus geometry

Fabricated products combine cutting, forming, welding, machining, surface treatment and assembly. Welding is the special process at the centre: it must be qualified, executed by qualified welders and inspected at the right stages.

Geometry is the second challenge. Distortion, fit-up errors and inadequate fixturing produce weldments that are structurally sound but cannot be assembled. QUALITAS TR covers both: welding quality to ISO 3834 principles and dimensional control of welded assemblies.

Machine frames and basesProcess skidsTanks and vesselsStructural assembliesStainless and hygienic fabricationAluminium fabricationHeavy plate fabrication

02Typical quality risks we see

  • Welding outside qualified ranges
  • Expired or unsuitable welder qualifications
  • Lack of fusion and incomplete penetration
  • Excessive distortion
  • Uncontrolled consumables
  • Missing traceability and weld maps
  • Repairs without procedure

03How QUALITAS TR supports welding and fabrication buyers

ServiceWhat we do in this sector
Welding InspectionBefore, during and after welding inspection to the specified quality level.
WPS, PQR and Welder Qualification ReviewWelding documentation review and qualification witnessing.
NDT Coordination and WitnessingNDT planning and review.
Dimensional and Geometrical InspectionDimensional and geometrical inspection of weldments.
Manufacturing and Special Process AuditsWelding process audits against ISO 3834 requirements.

04Key inspection points

  • WPS coverage per joint
  • Welder certificates and continuity
  • Consumable storage and baking
  • Fit-up and root gap
  • Preheat and interpass temperature
  • Visual inspection to ISO 5817 level
  • NDT extent and results
  • Dimensions after welding and stress relief
  • Weld map and traceability
  • Surface preparation before coating

Inspection and Test Plan: hold, witness and review points

A typical ITP sequence for a fabricated and machined assembly.

Example sequence
#ActivityReferenceSupplierThird partyRecord
1Pre-inspection meeting, ITP and drawing revision checkPO, specificationPHMinutes
2Material certificate review and identificationEN 10204 3.1PRMTC log
3WPS, PQR and welder qualification reviewISO 15614, ISO 9606PRReview sheet
4Fit-up and in-process weld visual inspectionISO 17637, ISO 5817PWWeld map
5NDT after final heat treatmentProject NDT procedurePWNDT reports
6Final dimensional inspectionDrawing, GD&TPHDimensional report
7Pressure or functional testTest procedurePHTest certificate
8Coating DFT, marking, packing and releaseCoating spec, packing specPHRelease note
P perform · H hold point: work stops until the inspector attends or waives · W witness point: inspector notified, work may proceed if not attending · R document review.

05Standards and requirements

Welding quality requirements are defined in ISO 3834 (comprehensive, standard or elementary). The appropriate part is chosen according to product criticality, often by the design code.

06The sector in Turkey

Turkey has a very large fabrication sector serving construction, energy, process industries and machinery, concentrated in Kocaeli, İstanbul, İzmir, Ankara and the steel producing regions.

Many fabricators hold ISO 3834 and EN 1090 certification; actual implementation varies, which audits reveal.

See the industrial cluster map

Direct contact. No forms.

Discuss your inspection, audit or project requirements

Send us the purchase order scope, drawings, specifications or ITP and the supplier location. You will receive a written proposal with scope, inspector profile, schedule and reporting format.

Emailinfo@qualitas.tr Telephone+90 533 197 19 81
OfficeBeştepe Mah. Nergiz Sok. 7/2 Kat:3 No: 87, Yenimahalle, Ankara, Turkey